The “Getting from here to there: Strategies for system migrations” e-Forum was held on March 26-27. Moderators included Buddy Pennington (University of Missouri – Kansas City), Emily Fidelman (West Virginia University), Anne LePage (Mount Allison University) and Cara Calabrese (Miami University in Ohio). The robust discussion included numerous stories of past migrations and tips and strategies to assist with future ones.
Participants shared their migration stories (either past or future). Mentioned platforms included TIND, Koha, Alma, Aleph, Voyager, Sierra, Millennium, WMS, CARL, and FOLIO. As many of the participants were from academic libraries, summer was mentioned as an opportune time to switch systems, as it is between semesters and, for many, between fiscal years as well. Participants mentioned being excited about new ERM functionality, the possibility of improved efficiencies and saving staff time, increasing communication and collaboration, and the ability to access and share data.
A recommendation mentioned many times was to plan to clean up your data before you migrate, as after you migrate you are so busy learning the new system that cleanup projects typically stay in your backlog. Schedule a migration after a major weeding project and/or plan to purge inactive records (including patron records) to reduce the volume of records to review during the migration. Review your items that are in transit, in repair, etc. A migration is also an opportune time to review and reduce material types, loan policies, shelving locations, and other similar categories.
Acquisitions and circulation data was mentioned as data that is sometimes not able to be migrated into a new system. Libraries need to be prepared to export and manage that data outside the new system if needed.
A couple of recommendations regarding migrating data included adding your record IDs from your old system to make it easier to compare records during the migration. Another was to have all of your MARC data available to ensure good mappings between systems and to be able to reference how the data was transformed. After implementing the new system, it is not uncommon for staff to ask why something looks different. Having a record of how the data migrated can answer those questions.
For migrations involving a large number of libraries or a consortia, a mentioned practice was having a select group of libraries migrate first. This provided an opportunity to both test and refine system settings and mappings and to provide recommendations and guidance for the other migrating libraries.
It was recommended that libraries work with vendors to provide multiple test loads as it can be very challenging to get the mappings correct the first time. It is generally easier to refine the mapping and then reload in the records than it is to clean up the problems later. Libraries should consider including support for multiple test loads in their RFP or contract expectations.
Staff training can be very challenging. While vendors provide training, it tends to be generalized so it can take some effort to adapt a library’s specific workflows to a new system. A combination of focused, functional training and open office hours for staff to bring specific questions can serve as a good mix, particularly for consortial migrations. Having access to a sandbox environment can work wonders in helping staff understand how to do their work in the system. Training on new features with system upgrades can help library staff stay current as the system changes over time.
It is good to be inclusive in who you include for technical configuration and mapping. Not only does that broaden the perspectives and allow for a wider range of thinking and consideration, but it also increases staff buy-in for the migration.
Last but not least, it is important for staff to take breaks, celebrate the successes and have fun when you can during a migration project. Migrations are challenging, but you’ll get through it!
Suggested Resources
- OhioLINK white paper on ILS expectations
- OCLC WMS Sandbox Access